10 Steps to Move In
-
Working based on our schedules/how fast we want to move on this.
-
Proposals are out and are becoming signed leases quickly
-
Space plans with their design team within a week
-
Included in price
-
-
CGDs (Construction Grade Drawings) take 3-6 weeks
-
They can connect us/underwrite architectural design team for us
-
can use part of $30 / sq. ft. build out
-
-
Permits are 3-5 weeks
-
Ready to sign the lease by the end of the year
-
Open bids to GCs (Gen. Contractors) in January
-
75 days of actual construction
-
Select and order furniture, etc.
-
April though August 2016 move in date