10 Steps to Move In 
  1. Working based on our schedules/how fast we want to move on this.
     

  2. Proposals are out and are becoming signed leases quickly
     

  3. Space plans with their design team within a week

    1. Included in price
       

  4. CGDs (Construction Grade Drawings) take 3-6 weeks

    1. They can connect us/underwrite architectural design team for us

    2. can use part of $30 / sq. ft. build out
       

  5. Permits are 3-5 weeks
     

  6. Ready to sign the lease by the end of the year
     

  7. Open bids to GCs (Gen. Contractors) in January
     

  8. 75 days of actual construction
     

  9. Select and order furniture, etc. 
     

  10. April though August 2016 move in date

     

     

     

     

     

     

     

     

     